Portfolio
Project: LeMoyne College Performing Arts Center,
Campus Center and Chapel, Syracuse, New York
(1995-1999)
Owner: LeMoyne College
Contract Amount: $7,200,000
Architect: Quinlivan, Pierik & Krause
References: Genevieve Saya 315-445-4120
Steven Krause 315-472-7806 |
 |
 |

 |
 |
 |
 |
Murnane was selected by LeMoyne College to
provide construction management services for a series of projects designed
to update the campus and improve student life. The projects included a
new Chapel (12,000 sq ft) completed in 1995, an addition and renovation
to the Campus Center (13,300 sq ft) completed in 1998 and a state-of-the-art
Performing Arts Center (25,000 sq ft) completed in 1999.
|
 |
 |
 |

 |
 |
 |
Murnane served as construction manager at risk
on each of the projects and completed all of the work under a GMP contract.
|
 |
For each of the individual projects, Murnane
provided preliminary estimates, value engineering and phasing/sequencing
planning services. |
 |
 |

 |
 |
 |
 |
In the end the project was completed under
budget by more than 2 percent with savings being returned to LeMoyne College.
“Murnane’s guidance and leadership skills provided
the balanced leadership which all parties needed.
The quality of workmanship is evident throughout.”
— Steven Krause, R.A., Project Architect |
 |

 |
 |
 |
 |
 |
 |
 |